Jira sprint report by assignee: committed, added, removed and completed per person

Last verified 31 October 2026Jira Cloud · 6 min read

Short answer. Jira's sprint report and velocity chart count the whole board and can't be split by assignee. For story points per person, you need each sprint's work items with their points and outcome. JQL gets you completed points per person for free; committed and added points per person need the work items' history.

What the sprint report and velocity chart count

  • Sprint report (Scrum boards, company-managed spaces): the work items in a sprint, completed or not, with those added after the start marked by an asterisk. It includes only work items that match the board's filter, and has no filter by person (Atlassian).
  • Velocity chart: Commitment is the total estimate of the sprint's work items when it starts; work added later and estimate changes don't count. Completed is the total of completed estimates when it ends, including work added during the sprint. Sub-task estimates are left out (Atlassian).

Both answer “how did the team do”. Neither answers “how did each person do”.

Sprint startsSprint ends
WEB-201 Ana · 5 ptsCompleted
WEB-202 Ben · 3 ptsCarried over
WEB-215 Ana · 2 ptsAdded · Completed
WEB-198 Ben · 3 ptsRemoved
Story pointsCommittedAddedCompleted
Ana527
Ben600
The sprint report shows the whole board. Split by assignee, the same sprint tells a different story.

Free: completed points per person with JQL

For a closed sprint, search for the work items done by its end date, then add up story points per assignee:

JQL, for a sprint that ended on 16 October 2026
sprint = "WEB Sprint 42" AND statusCategory = Done AND statusCategoryChangedDate <= "2026-10-16 23:59"
  1. Add the Assignee and Story point estimate (or Story Points) columns, then Export → Export Excel CSV (current fields).
  2. Import it into Google Sheets and insert a pivot table: rows = Assignee, values = SUM of the story points column.
  3. Repeat per sprint, or search several sprints at once and put Sprint in the pivot table's columns.

Use statusCategory = Done rather than status = Done, so every status in the Done category counts, whatever your workflow calls it.

Why the JQL numbers drift

  • Assignee is today's. A work item reassigned after the sprint counts for its new assignee.
  • Carried-over work items are in several sprints. Jira keeps every sprint an item was in, so an item finished in Sprint 43 also matches sprint = "WEB Sprint 42". The date condition above keeps those out.
  • Points are today's. If an estimate changed after the sprint, the export shows the new number.
  • Sub-tasks: exclude them with AND issuetype not in subTaskIssueTypes() if your team estimates stories only.

Committed and added need the history

JQL can't say which work items were in a sprint when it started, or what their points were then. That lives in each work item's history: the changes to its Sprint field, its status and its estimate. Replaying that history per sprint gives, for every work item, whether it was there at the start or added later, its points at the end, and whether it was completed, carried over or removed. With one row per work item per sprint, per-person numbers are a pivot table: rows = Assignee, columns = Sprint, values = SUM of Points, filtered on the outcome you want.

The history is available from Jira's REST API, one work item at a time, so a do-it-yourself script is a few hundred lines. Our add-on does it for you.

Cellmason for Jira

A Sprint report in Cellmason (Pro, $19/month per Jira site + applicable tax) reads a Scrum board's sprints and the history of their work items, and writes two tabs to Google Sheets. The Sprints tab has a row per sprint: committed, added, removed, completed and carried over, as work items and as points. The sprint issues tab has a row per work item per sprint:

ColumnWhat it holds
SprintThe sprint the row belongs to. A carried-over work item has a row in each sprint.
Assignee, and any field you pickAs they are now in Jira.
PointsStory points at the end of the sprint.
Status at sprint endThe status the work item had when the sprint closed.
JoinedAt start, or Added after the sprint began.
OutcomeCompleted, Carried over, Removed or Open (active sprint).
Carry-oversHow many earlier sprints the work item was in.

A pivot table on that tab gives points per person for every sprint, split by Joined and Outcome: what each person had at the start, what was added, and what they completed. Points are as they stood at the sprint's end, and like the JQL method, Assignee is the current assignee. Set the report to refresh daily and the active sprint stays current.